Date :09/19/2022
Project No :2021C001
Client Company :CW Matthews
Arrival Time :09/19/2022 19:00
Onsite Hours :07:30
Name of the Project :RAMP 19 & TAXILANE A3 PVMT REPLACEMENT,
Project Location :Atlanta
Weather :Clear
Departure Time :09/20/2022 02:30
ASEC Technician Name :Jared Barrios

Observations/Finding

Our ASEC representative arrived on site at 7:00 pm. The team of technicians was able to run three concrete sampling tests with the first test being the initial test. The team of technicians were able to create two sets of beams. Our ASEC technician departed at 2:30 am.

Technician Signature / DateJared Barrios, September 19, 2022
Reviewer Name / DateKenneth Mosman, October 23, 2022