Skip to content

Daily Field Report

Date :09/22/2022
Project No :2022C135
Client Company :Mark Spain
Arrival Time :09/22/2022 12:45
Onsite Hours :02:15
Name of the Project : Barnett Shoals Road Development
Project Location :Watkinsville
Weather :cloudy
Departure Time :09/22/2022 15:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, our ASEC technician was present at the above referenced site for the purpose of visually inspecting the south of the dam keyway.
The evaluation was performed by visual inspection and hand probing testing.

During the evaluation, soft soils, some with organics were encountered. We recommended the removal of approximately 3 feet of these unsuitable soils to reach residual soils.   Remedial work in this area took the rest of the day to complete.

See attached pictures.

Technician Signature / DateAminullah Azimi, September 22, 2022
Reviewer Name / DateKenneth Mosman, October 23, 2022