Skip to content

Daily Field Report

Date :09/08/2022
Project No :2021C002
Client Company :CW Matthews
Arrival Time :
Onsite Hours :
Name of the Project :Runway 9L End Around Taxiway
Project Location :HJAIA
Weather :
Departure Time :
ASEC Technician Name :Nick Smith

Observations/Finding

9/08/22

As requested by CWM James Higgins, the site was visited by our AS Engineering and Consulting (ASEC) representative noted above, for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

Site Observations:

Contractor continued work in E-Line between E1 to E2, I-Line between I3-I4, and the ravine area around STA 409+00 of the taxiway. Fill was placed and compaction testing requested. Riprap stone was continued to be placed and densified in the ravine as according to the plans.

Density testing was performed using a Troxler nuke gauge (#3430, serial #29588).

Density testing results:
P14 Moisture Density Relationship (proctor) – 119.8 pcf @ 14.0%

T1 – elevation 986.5, 15′ north of I3, P14, DD 119.4, M% 12.6, compaction 99.7%

T2 – elevation 986.5, 15′ south of I4, P14, DD 115.8, M% 12.1, compaction 96.7%

Technician Signature / DateNick Smith, September 8, 2022
Reviewer Name / DateKenneth Mosman, October 23, 2022