8/05/22
As requested by CWM James Higgins, the site was visited by our AS Engineering and Consulting (ASEC) representative noted above, for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
Site Observations:
Contractor worked around the A8 structure, excavating and backfilling the area because of previous low compaction results.
The Localizer area displayed high moisture contents (17-22%) and needed to be scarified and aerated, however, this could not be completed today before rain/lightning started and ended the workday.