Observations/Finding
As requested, the site was visited by the AS Engerineering and Consulting (ASEC) representative noted above, for the purpose of providing quality control inspection and testing services, visual observation techniques were employed to assure compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
Contractor continued work on the dam keyway, south side and north side of keyway of dam. Fill was placed and spread using a dozer with the ground crew collecting and removing oversized materials. Compaction was performed using a D51pxi., sheeps-feet roller and dump truck.
Density testing was performed using a Troxler nuclear gauge (#3430, serial #29588).
Density testing result:
P-1 Moisture-Density Relationship (proctor) = 97.3 @ 23.7%
T1-elevation -8.5′ from top of keyway P-1, Yd 98.3 M%24.2, Compaction: 101%
T2-elevation -8′ from top of keyway P-1, Yd 97.6, M%26.4, Compaction: 100.3%
T3-elevation -8′ from top of keyway P-1, Yd 94.2, M% 25.1, Compaction: 96.6%
T4-elevation -8′ from top of keyway P-1, Yd 96.5, M%25.7, Compaction: 99.2%
T5-elevation -8′ from top of keyway P-1, Yd 97.8, M%25.1, Compaction: 100.5%