Date :04/29/2022
Project No :2022C128
Client Company :Century
Arrival Time :04/29/2022 08:00
Onsite Hours :02:30
Name of the Project :Sidney Square, Flowery Branch
Project Location :Flowery Branch
Weather :
Departure Time :04/29/2022 10:30
ASEC Technician Name :Rasheen Biggins

Observations/Finding

The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today.

Upon arrival to the project site, our ASEC representative found that work was already in progress. Contractors were placing fill on the lot near the shoulder of the adjacent road. Remediation recommended on April 28 was being performed in the decel lane.

Technician Signature / DateRasheen Biggins, April 29, 2022
Reviewer Name / DateKenneth Mosman, November 13, 2022