- Density Test Report Report ID: 55458
- Edit Download Report
Density Test Report
Date :11/08/2022
Project No :2022C165
Client Company :Toll Bros. Inc.
Arrival Time :11/08/2022 08:00
Onsite Hours :07:00
Name of the Project :Northfield @ Polo Fields - Phase2
Project Location :Pittman Road, Cumming, GA
Weather :Sunny
Departure Time :11/08/2022 15:00
ASEC Technician Name :Vidal Dias
Observations/Finding
Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
---|---|---|---|---|---|---|---|---|---|---|
11/08/2022 | Test 1 | 23 | 88.0 | 3 | 99.4 | 21.3 | 88.5 | 95 | D6938 | Fail |
Location : | see attached Daily Field Report, Elv/Depth :1060 | |||||||||
Comment : | Area requires recompaction and retesting prior to continued fill placement | Gauge Serial No. : | ||||||||
11/08/2022 | test 2 | 17.3 | 111.3 | 3 | 99.4 | 21.3 | 112.0 | 95 | D6938 | Pass |
Location : | see attached Daily Field Report, Elv/Depth :1080 | |||||||||
Comment : | Gauge Serial No. : | |||||||||
11/08/2022 | test 3 | 21 | 93.7 | 3 | 99.4 | 21.3 | 94.3 | 95 | D6938 | Fail |
Location : | see attached Daily Field Report, Elv/Depth :1070 | |||||||||
Comment : | Area requires recompaction and retesting prior to continued fill placement | Gauge Serial No. : |
Technician Signature / DateVidal Dias, November 8, 2022
Reviewer Name / DateKenneth Mosman, April 07, 2023