Daily Field Report

Date :05/06/2022
Project No :2022C128
Client Company :Century
Arrival Time :05/06/2022 07:30
Onsite Hours :04:30
Name of the Project :Sidney Square, Flowery Branch
Project Location :Flowery Branch
Weather :
Departure Time :05/06/2022 12:00
ASEC Technician Name :Rasheen Biggins

Observations/Finding

The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today.

Upon arrival, our ASEC representative observed that the contractor already had work in progress. Contractor was placing fill, with each lift approximately 8in-10in in thickness.  Contractor utilized a bulldozer Komatsu 61px for spread, and a sheeps-foot Caterpillar Compactor. All density test results were reported back to the contractor and are attached.

Technician Signature / DateRasheen Biggins, May 6, 2022
Reviewer Name / DateKenneth Mosman, November 13, 2022