- Home
- Daily Field Report Report ID: 55513
- This project is inactive from admin.Download Report
Daily Field Report
Date :05/19/2022
Project No :2022C128
Client Company :Century
Arrival Time :05/19/2022 12:00
Onsite Hours :06:30
Name of the Project :Sidney Square, Flowery Branch
Project Location :Flowery Branch
Weather :
Departure Time :05/19/2022 18:30
ASEC Technician Name :Rasheen Biggins
Observations/Finding
The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today.
Upon arrival to the project site, our ASEC representative observed that work was already in progress. The contractor was excavating approximately 60 feet to lay pipeline near the sidewalk adjacent to Mcever Rd. Using a 3/8″ diameter probe rod, the area was deemed stable for backfill placement.
Technician Signature / DateRasheen Biggins, May 19, 2022
Reviewer Name / DateKenneth Mosman, November 13, 2022