Daily Field Report

Date :06/02/2022
Project No :2022C136
Client Company :Century
Arrival Time :06/02/2022 13:00
Onsite Hours :05:30
Name of the Project :Logan Pointe
Project Location :Loganville
Weather :
Departure Time :06/02/2022 18:30
ASEC Technician Name :Rasheen Biggins

Observations/Finding

The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today.

Upon arrival to the project site, our ASEC representative observed that work was already in progress. Contractor continued placing fill in the creek area and the adjacent field area. Each lift placed was approximately 8 to 10 inches in thickness. Density tests were taken after each lift and results reported back to the contractor. Density test results can be found in the attached report. Contractor was also concerned about an area located approximately 30 feet south of the river.  Groundwater levels appeared to rise as excavating activities continued.

Technician Signature / DateRasheen Biggins, June 2, 2022
Reviewer Name / DateKenneth Mosman, November 13, 2022