Density Test Report

Date :06/02/2022
Project No :2022C136
Client Company :Century
Arrival Time :06/02/2022 13:00
Onsite Hours :05:30
Name of the Project :Logan Pointe
Project Location :Loganville
Weather :
Departure Time :06/02/2022 18:30
ASEC Technician Name :Rasheen Biggins

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
06/02/2022 1 20.1 102.4 P-1 99.0 21.4 103.4 95 D6938 Pass
Location : in the creek area, Elv/Depth :
Comment : Gauge Serial No. :38069
06/02/2022 2 20.9 103.0 P-1 99.0 21.4 104.0 95 D6938 Pass
Location : In the creek area , Elv/Depth :
Comment : Gauge Serial No. :38069
06/02/2022 3 17.3 106.1 P-1 99.0 21.4 107.2 95 D6938 Pass
Location : In the creek area, Elv/Depth :
Comment : Gauge Serial No. :38069
06/02/2022 4 15.7 102.2 P-1 99.0 21.4 103.2 95 D6938 Pass
Location : In the field area , Elv/Depth :
Comment : Gauge Serial No. :38069
06/02/2022 5 10.2 105.6 P-1 99.0 21.4 106.7 95 D6938 Pass
Location : In the field area, Elv/Depth :
Comment : Gauge Serial No. :38069
06/02/2022 6 24.1 89.6 P-1 99.0 21.4 90.5 95 D6938 Fail
Location : In the field area, Elv/Depth :
Comment : Moisture content much higher than optimum. Recommended contractor scarify and aerate prior to recompacting. Gauge Serial No. :38069
Technician Signature / DateRasheen Biggins, June 2, 2022
Reviewer Name / DateKenneth Mosman, November 13, 2022