Skip to content

Daily Field Report

Date :06/06/2022
Project No :2022C128
Client Company :Century
Arrival Time :06/06/2022 07:30
Onsite Hours :05:30
Name of the Project :Sidney Square, Flowery Branch
Project Location :Flowery Branch
Weather :
Departure Time :06/06/2022 13:00
ASEC Technician Name :Rasheen Biggins

Observations/Finding

The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today

Upon arrival to the project site, our ASEC representative observed work was already in progress.  Contractors were placing fill in the field area. Each lift placed was approximately 8 to 10 inches in thickness. After each lift was placed density tests were taken and reported back to the contractor. Materials were placed by a bulldozer 61px and compaction performed by a sheeps-foot compactor.  Density test results are attached.

Technician Signature / DateRasheen Biggins, June 6, 2022
Reviewer Name / DateKenneth Mosman, November 13, 2022