Daily Field Report

Date :11/09/2022
Project No :2022C165
Client Company :Toll Bros. Inc.
Arrival Time :11/09/2022 06:30
Onsite Hours :02:30
Name of the Project :Northfield @ Polo Fields - Phase2
Project Location :Pittman Road, Cumming, GA
Weather :Sunny
Departure Time :11/09/2022 09:00
ASEC Technician Name :Vidal Dias

Observations/Finding

AS Engineering and Consulting, LLC (ASEC) visited the site at the client’s request to perform footing inspections for Lots #6,8,9,10,12 and 13. During the evaluation, well-compacted fill soils were encountered underlain by residual soils within the planned building pad area.

Lots #8 and 9 refused at two feet using DCP equipment.

One DCP was taken in the remediated area of Lot #10 (outlined in red on the attached image).  The area was probed, and one DCP test was performed; well-compacted soils were encountered at the base of each pier.

 

 

Technician Signature / DateVidal Dias, November 9, 2022
Reviewer Name / DateKenneth Mosman, April 07, 2023