Daily Field Report

Date :11/09/2022
Project No :2022C136
Client Company :Century
Arrival Time :11/09/2022 7:00
Onsite Hours :06:30
Name of the Project :Logan Pointe
Project Location :Loganville
Weather :Sunny
Departure Time :11/09/2022 13:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, the site was visited by the AS Engerineering and Consulting (ASEC) representative noted above, for the purpose of providing quality control inspection and testing services, visual observation techniques were employed to assure compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

Contractor continued work on Lots #58 to 63 and from Lots #41 to 45. Fill was placed and spread using a dozer. Compaction was performed using a D51pxi sheeps-foot roller and dump truck. 

Density testing was performed using a Troxler nuclear gauge (#3430, serial #85759).

Density testing result:

P-3 Moisture-Density Relationship (proctor) = 96.5 @ 22.2%

T1-elevation -2′ from finish grade P-3, Yd 87.7M%25.6, Compaction: 90.9%

T2-elevation -2′ from finish grade P-3, Yd 89.3M%22.3, Compaction: 92.5%

T3-elevation -2′ from finish grade P-3, Yd 93.5%24.1, Compaction: 96.9%

T4-elevation -2′ from finish grade P-2, Yd 104.0M%15 Compaction: 105.3%

T5-elevation -2′ from finish grade P-3, Yd 90.1 M%24.7, Compaction: 93.5%

Technician Signature / DateAminullah Azimi, November 9, 2022
Reviewer Name / DateKenneth Mosman, November 13, 2022