Skip to content

Daily Field Report

Date :01/24/2023
Project No :2022C227
Client Company :Artisan
Arrival Time :01/24/2023 12:30
Onsite Hours :05:30
Name of the Project :Riverwalk Manor (CMT) Unit 2, PH 4E and 4F
Project Location :Dallas
Weather :Sunny
Departure Time :01/24/2023 18:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, our AS Engerineering and Consulting (ASEC) representative visited the site for the purpose of providing quality control inspection and testing services, visual observation techniques were employed to assure compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

Contractor continued backfill for Lots #421, #422, #423 and the roadway.

Upon arrival, work was already in progress.  Contractor was placing 12-inch lifts with compaction performed using a Caterpillar 815 F.

Density testing was performed using a Troxler nuclear gauge (#3430, serial #85759). 

Density test results indicate that the compacted materials met the project specfication of 90% of the maximum dry density obtained by the (Standard Proctor ASTM 698). 

Density testing result:

P-01 Moisture-Density Relationship (proctor) = 100.4 pcf @18.6%

T1-elevation -15 feet from finish grade. Yd 104.1 M%15.1, Compaction: 103.6 %

T2-elevation -15 feet from finish grade Yd 97.7, M%18.1, Compaction: 97.3%

T3-elevation -15.5 feet from finish grade, Yd 97.3, M%16.6, Compaction: 96.9 %

T4-elevation -15.5 feet from finish grade, Yd 101.03, M%15.5, Compaction: 100.9 %

T5-elevation -15.5 feet from finish grade, Yd 94.9, M%18, Compaction: 94.5 %

Technician Signature / DateAminullah Azimi, January 24, 2023
Reviewer Name / DateKenneth Mosman, January 29, 2023