Daily Field Report

Date :01/25/2023
Project No :2022C227
Client Company :Artisan
Arrival Time :11/18/2022
Onsite Hours :
Name of the Project :Riverwalk Manor (CMT) Unit 2, PH 4E and 4F
Project Location :Dallas
Weather :cloudy
Departure Time :11/18/2022
ASEC Technician Name :Russell Hendrix

Observations/Finding

As requested, the site was visited by our AS Engerineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services, visual observation techniques were employed to assure compliance with project drawing/specifications, applicable codes, and materials submittals. the following observations were observed on site this day.

Various earth moving equipment were observed continuing placing topsoil on slopes behind Lot #422 (see photo).  No compactor was running on this day (down for maintenance).

Technician Signature / DateRussell Hendrix, January 25, 2023
Reviewer Name / DateKenneth Mosman, January 29, 2023