- Home
- Daily Field Report Report ID: 56315
- Edit Download Report
Daily Field Report
Date :01/25/2023
Project No :2022C227
Client Company :Artisan
Arrival Time :01/07/2023
Onsite Hours :
Name of the Project :Riverwalk Manor (CMT) Unit 2, PH 4E and 4F
Project Location :Dallas
Weather :cloudy
Departure Time :01/07/2023
ASEC Technician Name :Russell Hendrix
Observations/Finding
As requested, our AS Engerineering and Consulting (ASEC) representative arrived on site for the purpose of providing quality control inspection and testing services, visual observation techniques were employed to assure compliance with project drawing/specifications, applicable codes, and materials submittals. the following observations were observed on site this day.
Upon arrival, various earth moving equipment (excavator, dozer, off road dump trucks, 815F Caterpillar compactor) were placing topsoil on slopes behind Lots #421, #422, & #423. A berm was constructed behind future Lot #422 in anticipation of water run-off from expected future rain events. (see photos)
Technician Signature / DateRussell Hendrix, January 25, 2023
Reviewer Name / DateKenneth Mosman, January 29, 2023