- Home
- Daily Field Report Report ID: 56582
- This project is inactive from admin.Download Report
Daily Field Report
Date :02/08/2023
Project No :2022C235
Client Company :Jackson Demolition Service, Inc.
Arrival Time :02/08/2023 06:00
Onsite Hours :10:15
Name of the Project :Plant Gorgas Demolition and Grading
Project Location :460 Gorgas Rd, Parrish, AL 35580
Weather :Partly Cloudy
Departure Time :02/08/2023 16:20
ASEC Technician Name :Vidal Dias
Observations/Finding
AS ENGINEERING AND CONSULTING, LLC (ASEC) representative Vidal Dias visited the site at the request of Jackson Demolition representative Josh Kelly. The undersigned representative was present to monitor, verify and document the ongoing project activities.
During the visit, the following observations were made:
- The contractor installed 796.77 tons of No. 24 stone over the previously prepared Terragrid layer in the lower half of the basement areas G7 and G8.
- No. 24 stone was placed according to the specification on drawing sheet E720667.
Photo documentation is included below:
24 stone placement area G8
24-stone-placement area G8-2
24 stone at grade area G7
24 stone at grade area G8
24 stone placement area G7
Technician Signature / DateVidal Dias, February 8, 2023
Reviewer Name / DateRamchandra Mogulla, February 09, 2023