Daily Field Report
Observations/Finding
As requested, our AS Engerineering and Consulting (ASEC) representative visited the site for the purpose of providing quality control inspection and testing services, visual observation techniques were employed to assure compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
Contractor continued backfilling and compaction for Lots #422, #423, #424, #426 and the roadway.
Upon arrival, work was already in progress with contractor placing lifts, approximately 16 inches in thickness.
The soils observed on this date did not appear to be placed in accordance with project specifications (overly thick lifts placed).
The contractor was notified about the excessive lift thicknesses.
Density testing was performed using a Troxler nuclear gauge (#3430, serial #85759).
Density test results indicate that the compacted material met project specifications of 90% of the maximum dry density obtained by the (Standard Proctor ASTM 698).
Density testing result:
P-01 Moisture-Density Relationship (proctor) = 100.4pcf @ 18.6%
T1-elevation -6.5 feet from finish grade@ lot 422, Yd 100.3 M%16.1, Compaction: 99.9 %
T2-elevation -3.5 feet from finish grade@ road, Yd 97.8 M%15.9, Compaction: 97.4 %
T3-elevation -4.5 feet from finish grade@ lot 426 Yd 93.9, M%16, Compaction:93.5 %
T4-elevation -9 feet from finish grade@ road, Yd 94.4, M%17.5, Compaction: 94%
T5-elevation -3.5 feet from finish grade@ lot 424, Yd 94.8, M%16, Compaction: 94.4 %
T6-elevation – 7.5 feet from finish grade@ lot 423, Yd 100.7, M%16.2, Compaction: 100.3 %