Daily Field Report

Date :03/03/2023
Project No :2023C111
Client Company :2MATL
Arrival Time :03/03/2023 11:30
Onsite Hours :06:00
Name of the Project :DOA Fiber Infrastructure Improvements
Project Location :HJAIA
Weather :cloudy
Departure Time :03/03/2023 17:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

Our AS Engineering & Consulting (ASEC) representative arrived on site, as requested, to observe:  the placement of concrete and backfill for the DOA fiber infrastructure.

Upon arrival, concrete was already placed, and the contractor notified that concrete placement took place earlier than the scheduled time. Backfilling activities were canceled due to rain.

 

Technician Signature / DateAminullah Azimi, March 3, 2023
Reviewer Name / DateKenneth Mosman, March 14, 2023