- Daily Field Report Report ID: 57402
- This project is inactive from admin.Download Report
Daily Field Report
Date :03/02/2023
Project No :2022C235
Client Company :Jackson Demolition Service, Inc.
Arrival Time :
Onsite Hours :
Name of the Project :Plant Gorgas Demolition and Grading
Project Location :460 Gorgas Rd, Parrish, AL 35580
Weather :
Departure Time :
ASEC Technician Name :Vidal Dias
Observations/Finding
Our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative Vidal Dias visited the site at the
request of Jackson Demolition representative Josh Kelly. The undersigned representative was present to
observe, verify and document the ongoing project activities.
During the visit, the following observations were made:
- The contractor placed textile fabric over the concrete trench, and two 20-inch HDPE pipes I.D (18″) O.D 21″ were placed atop the textile fabric in the south trench located in area F7.
- No. 57 stone was placed between pipes and trench walls, up to 4″ inches of cover to the top of the pipe.
- No. 57 and No. 24 stone was placed up to eight (8) inches below the finished grade.
- Materials were placed in accordance with ITP: 13
Photo documentation is included below:
Technician Signature / DateVidal Dias, March 2, 2023
Reviewer Name / DateRamchandra Mogulla, March 06, 2023