Skip to content

Daily Field Report

Date :03/07/2023
Project No :2022C235
Client Company :Jackson Demolition Service, Inc.
Arrival Time :03/07/2023 06:00
Onsite Hours :10:30
Name of the Project :Plant Gorgas Demolition and Grading
Project Location :460 Gorgas Rd, Parrish, AL 35580
Weather :Sunny
Departure Time :03/07/2023 16:30
ASEC Technician Name :Vidal Dias

Observations/Finding

AS ENGINEERING AND CONSULTING, LLC (ASEC) representative Vidal Dias visited the site at the request of Jackson Demolition representative Josh Kelly. The undersigned representative was present to monitor, verify and document the ongoing project activities.

During the visit, the following observations were made:

  1. The contractor received thirty-nine (39) loads of fill material and placed it in area H8 of the basement. Fill was placed in accordance with ITP-001. Material was placed in 2 foot lifts as part of the planned bridge lift. No testing was performed on this day at the lift was not ready to be assessed.
  2. Steel plates were placed to screen the HDPE pipe openings in the north and south trenches in accordance with ITP-012. 
  3. Riprap was placed adjacent to the steel plates in both trenches. 

Photo documentation is included below: 

Steel plates between pipe and rip rap in north trench

Steel plates between pipe and rip rap in south trench

Steel plates cover the pipe opening in the south trench. Four 5" - 6" holes were cut in steel to facilitate water flow and prevent rip rap from migrating into drains.

Steel plates cover pipe opening in the north trench. Four 5" - 6" holes were cut in steel to facilitate water flow and prevent rip rap from migrating into drains.

Technician Signature / DateVidal Dias, March 7, 2023
Reviewer Name / DateRamchandra Mogulla, March 09, 2023