Daily Field Report

Date :03/16/2023
Project No :2022C235
Client Company :Jackson Demolition Service, Inc.
Arrival Time :03/16/2023 06:00
Onsite Hours :10:30
Name of the Project :Plant Gorgas Demolition and Grading
Project Location :460 Gorgas Rd, Parrish, AL 35580
Weather :
Departure Time :03/16/2023 16:30
ASEC Technician Name :Vidal Dias

Observations/Finding

Our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative Vidal Dias visited the site at the request of Jackson Demolition representative Josh Kelly. The undersigned representative was present to observe, verify and document the ongoing project activities.

During the visit, the following observations were made:

  1.  774 Yards (43 loads) of clay material were received and placed in the basement at sections H7 and H8.
  2. The fill material was placed and compacted in the basement in accordance with ITP-001.
  3. 825B and crushed concrete were placed in sections H6, G6, and F6, compacted using CAT CS54B, and proof-rolled using a tandem axle water truck. The proof-rolled area is highlighted in purple on the attached drawing.
  4. During the proof roll, no significant rutting or deflection was revealed except in an area approximately 20-30 feet near the embankment adjacent to the intake canal in Baker’s Creek. The area is highlighted in red on the attached drawing; these areas were marked on-site with white paint. This area is not acceptable for the placement of planned pavement.

Photo documentation is included below:

Fill material being compacted in basement

Area H6 being compacted

Crushed concrete being placed near the inlet in H6

Crushed concrete being placed

Water truck conducting proof roll in area H6

Water truck conducting proof roll in area G6

Rutting in area F6.

Technician Signature / DateVidal Dias, March 16, 2023
Reviewer Name / DateRamchandra Mogulla, March 26, 2023