Daily Field Report

Date :03/22/2023
Project No :2022C235
Client Company :Jackson Demolition Service, Inc.
Arrival Time :03/22/2023 06:00
Onsite Hours :10:30
Name of the Project :Plant Gorgas Demolition and Grading
Project Location :460 Gorgas Rd, Parrish, AL 35580
Weather :
Departure Time :03/22/2023 16:30
ASEC Technician Name :Vidal Dias

Observations/Finding

Our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative Vidal Dias visited the site at the request of Jackson Demolition representative Josh Kelly. The undersigned representative was present to observe, verify and document the ongoing project activities. (Reference drawing E720661 S1 – R5 & E720659 S1-R5.)

During the visit, the following observations were made:

1.Five hundred fifty-eight (558) square yards of fill material were placed and compacted for the bridge lift in the basement in accordance with ITP-001.
2.The area was hand probed using a 3/8″ diameter probe rod during the placement and the probe did not exceed 1.5 inches into the soil.
3.The contractor constructed the slope in area F6 on the west side of the intake canal. The slope area was probed, and no significant rutting or deflection was encountered.
4. The compaction test for the area passed (Please review the attached)
5. Two steel plates were placed over the drainage pipe in area F7.

Photo documentation and test locations are attached:

Technician Signature / DateVidal Dias, March 22, 2023
Reviewer Name / DateRamchandra Mogulla, April 06, 2023