Daily Field Report

Date :03/04/2023
Project No :2023C111
Client Company :2MATL
Arrival Time :03/04/2023
Onsite Hours :
Name of the Project :DOA Fiber Infrastructure Improvements
Project Location :HJAIA
Weather :sunny
Departure Time :03/04/2023
ASEC Technician Name :Russell Hendrix

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative noted above, for the purpose of providing quality control inspection and testing services, visual observation techniques were employed to assure compliance with project drawing/specifications.

A request was made for soil density testing for the backfilling of the installation of pipe for fiber cables.  Kerri the foreman with BBH was onsite.  All work was performed within a 2-foot deep trench located behind the Technical Campus.  The trench had previously been filled with concrete.  M10 sand, with a Density-Moisture ratio (proctor) with an optimum of 122.6 Dry Density (DD) and 10.8% Moisture (M) was used.   The lifts were placed in 6-8 inches and compacted with a trench packer.

No further observations were made.

 

 

 

Technician Signature / DateRussell Hendrix, March 4, 2023