Daily Field Report

Date :03/16/2023
Project No :2022C128
Client Company :Century
Arrival Time :
Onsite Hours :
Name of the Project :Sidney Square, Flowery Branch
Project Location :Flowery Branch
Weather :sunny
Departure Time :03/16/2023
ASEC Technician Name :Russell Hendrix

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative noted above, for the purpose of providing quality control inspection and testing services, visual observation techniques were employed to assure compliance with project drawing/specifications.

A request was made to test the clubhouse parking lot with a 2nd proof-roll.  Remediation from the previous day (including 2 lifts) was not observed.  Upon placing approximately 18 inches of crushed stone, a loaded tandem axel dump truck was used for the proof-roll.  Significant movement was still observed throughout the parking lot area.  A recommendation by Ram Mogulla, ASEC PE, of using textile fabric was given.  DRH elected to not follow the recommendation.  Asphalt paving started without any remediation.

 

 

Technician Signature / DateRussell Hendrix, March 16, 2023
Reviewer Name / DateKenneth Mosman, April 02, 2023