Skip to content

Daily Field Report

Date :04/04/2023
Project No :2022C235
Client Company :Jackson Demolition Service, Inc.
Arrival Time :04/04/2023 06:00
Onsite Hours :10:30
Name of the Project :Plant Gorgas Demolition and Grading
Project Location :460 Gorgas Rd, Parrish, AL 35580
Weather :Mostly Cloudy
Departure Time :04/04/2023 16:30
ASEC Technician Name :Vidal Dias

Observations/Finding

Our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative Vidal Dias visited the site at the request of Jackson Demolition representative Josh Kelly. The undersigned representative was present to observe, verify and document the ongoing project activities. (Reference drawing E720661 S1 – R5, E720659 S1-R5.)

During the visit, the following observations were made:

  1. One thousand seven hundred sixty-four (1764) cubic yards of fill materials were placed for lift two in section 2 area G6 & G7 (drawing E720659) of the basement. The materials were placed in accordance with ITP-001, and the fill area is highlighted in orange on the attached drawing.
  2. Two (2) moisture content and density tests were performed in section 1, area B7; the results were within acceptable limits. The test locations are shown in green on the attached drawing.

Photo documentation and test locations are attached:

4_4_Lift 2_section 2_Test locations

Technician Signature / DateVidal Dias, April 4, 2023
Reviewer Name / DateRamchandra Mogulla, April 06, 2023