- Concrete Test Report Report ID: 58976
- Edit Download Report
Concrete Test Report
Date :04/21/2023
Project No :2023C111
Client Company :2MATL
Arrival Time :04/21/2023 07:00
Onsite Hours :04:00
Name of the Project :DOA Fiber Infrastructure Improvements
Project Location :HJAIA
Weather :Sunny
Departure Time :04/21/2023 11:00
ASEC Technician Name :Isaac Davis
Concrete Placement Information
Location(S):
Testing:
One set Set of concrete specimens (6 Cylinders per set) were cast during the cast-in-place concrete pour at the above referenced location, in accordance with ASTM C31. The cylinders will remain on site for the initial 24-48 hrs curing.
Compliance:
Field placement of concrete appeared to be in accordance with the project specifications (i.e., slump, temperature, etc) (refer to remarks below)
Deviations and/or noncompliances were noted during the field placement (refer to remarks below)
Cylinders
Pick Up: One set Sets of concrete cylinders/ 6 cylinders per set were picked up & transported to AS Engineering and Consulting LLC (ASEC) for curing and testing in accordance with ASTM C39, C670/1231
Pick Up: One set Sets of concrete cylinders/ 6 cylinders per set were picked up & transported to AS Engineering and Consulting LLC (ASEC) for curing and testing in accordance with ASTM C39, C670/1231
Field Curing:
Cylinders were stored for the initial 24 hours
Near the poured structure
In an insulated curing box
Other
Remarks:
Once arrived at the project for the concrete placement, I followed up on another observation of project to make sure everything was still acceptable.
When the testing was completed, the Air was not in compliance with specifications. I discussed with the contractor about the air not falling into specification.
On the second load another Air check was completed, and the air came up to 1.3%. The contractor was informed as well of the air not being in compliance with specifications.
slump: 4.75
air: 2.5%
temp: 63
unit weight: 144.4 pcf
air re-check: 1.3 %
Field Test Data
Set Number :
Date Sampled :04/21/2023
Sampled By :Isaac Davis
Contractor :Athena
Truck Number :239
Time Batched :07:26
Location of Placement :Generator pad at Vault #2
Number of samples cast :6
Ambient Temperature (°f) :59
Slump (in.) :4.75
Water added (gal.) :1
Laboratory Number :
Time Sampled :07:53
Weather Condition :Sunny
Concrete Supplier :Ernest
Mix ID :45CA65
Quantity of Load (cu. yd.) :9
Sample Cast :One set
Specified Strength :4500
Concrete Temperature(°f) :63
Air Content (%) :2.5
Strength Test Results
Specimen Number | Age (days) | Date Tested | Dia(in.) | Area (sq in.) | Maximum Loads (lbs) | Strength (lbs) | % Design Strength | Type of Fracture |
---|---|---|---|---|---|---|---|---|
1 | ||||||||
2 | ||||||||
3 | ||||||||
4 | ||||||||
5 | ||||||||
6 |
UNLESS OTHERWISE SPECIFIED, TESTS WERE PERFORMED IN ACCORDANCE WITH ASTM TEST METHODS C31, C39, C138, C143, C173, AND C1064. FRACTURE TYPE INDICATED BY NUMBER.
(Type 1) Cone (Type 2) Cone-split (Type 3) Vertical (Type 4) Shear (Type 5) Edge Fracture (Type 6) Pointed
Technician Signature / DateIsaac Davis, April 21, 2023
Reviewer Name / DateKenneth Mosman, May 07, 2023