Skip to content

Daily Field Report

Date :05/04/2023
Project No :2022C235
Client Company :Jackson Demolition Service, Inc.
Arrival Time :05/04/2023 06:00
Onsite Hours :10:30
Name of the Project :Plant Gorgas Demolition and Grading
Project Location :460 Gorgas Rd, Parrish, AL 35580
Weather :SUNNY
Departure Time :05/04/2023 16:30
ASEC Technician Name :Avinash Bandham

Observations/Finding

AS ENGINEERING AND CONSULTING, LLC (ASEC) representative Avinash Bandam visited the site at the request of Jackson Demolition representative Josh Kelly. The undersigned representative was present to monitor, verify and document the ongoing project activities. (Reference drawing E720661 S1 – R5, E720659 S1-R5.)

During the visit, the following observations were made:

    1. Two thousand three hundred and fifty eight (2358) cubic yards of fill materials were placed for lift (10) in section 1 area B7 (drawing E720661) of the basement. The materials were placed and compacted in accordance with ITP-001. The blue highlighted area in the drawing E720661shows the placement of the fill material in the section 1.
    2. The edges of the North, East, West and South walls of the section 2 in basement has probed using the hand probe as requested by client Mr. Terry Polena representative of Jacksonville Demolition.

 

Placement of Lift-10 in the section-1 basement area B7.

Compaction using the roller and dozer.

Loads received and delivered to the site for the placement in section-1.

Technician Signature / DateAvinash Bandham, May 4, 2023
Reviewer Name / DateRamchandra Mogulla, May 05, 2023