Daily Field Report

Date :05/11/2023
Project No :2022C113
Client Company :CWM
Arrival Time :05/11/2023 14:30
Onsite Hours :03:30
Name of the Project :Airfield Sewer Enhancements
Project Location :HJAIA
Weather :sunny
Departure Time :05/11/2023 18:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services, visual observation techniques were employed to assure compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

The placement and compaction of backfill soils for the sewer pipe trench between manholes, MH 2 to MH 3, continued this day.

At the time of arrival, our representative observed that work was in progress with lifts being placed at about 2 feet below finished grade and compacted using a trench compactor.

The test results are on standby until the moisture-density relationship for these materials is performed.

Technician Signature / DateAminullah Azimi, May 11, 2023
Reviewer Name / DateKenneth Mosman, July 08, 2023