Skip to content

Daily Field Report

Date :05/18/2023
Project No :2022C113
Client Company :CWM
Arrival Time :05/18/2023 7:30
Onsite Hours :06:00
Name of the Project :Airfield Sewer Enhancements
Project Location :HJAIA
Weather :cloudy
Departure Time :05/18/2023 13:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services, visual observation techniques were employed to assure compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

The placement and compaction of sewer trench with GAB between MH2 and MH3 continued this day.

At the time of arrival, our representative observed that work was continued with materials being placed to 1 foot below finished grade and compacted using a trench compactor.

Density test results indicate that the compacted materials met the project requirement of 90%.

Technician Signature / DateAminullah Azimi, May 18, 2023
Reviewer Name / DateKenneth Mosman, July 08, 2023