Daily Field Report
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services, visual observation techniques were employed to assure compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
The placement and compaction of GAB for taxiway 6B shoulder attached to lane 4 and lane 5 continued this day.
At the time of arrival, our representative observed that work was in progress near finished grade and compacted using a trench compactor.
Density test results indicate that the compacted materials met the project requirement of 95%.
Our representative also observed straightedge on taxiway 6B. A 3/8-inch low spot was observed in lane 1 panel 2, traveling north. Craig with AtLnext was notified.