Skip to content

Daily Field Report

Date :06/09/2023
Project No :2022C227
Client Company :Artisan
Arrival Time :06/09/2023 8:00
Onsite Hours :03:30
Name of the Project :Riverwalk Manor (CMT) Unit 2, PH 4E and 4F
Project Location :Dallas
Weather :sunny
Departure Time :06/09/2023 11:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services, visual observation techniques were employed to assure compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

The placement and compaction of backfill soils for Lots #412, 416 and 417 continued this day.

At the time of arrival, our representative observed that soils were already compacted with lifts being placed to finished grade and compacted using a 810 compactor.

Density test results indicate that the compacted materials met the project requirement of 90% at finished grade.

Technician Signature / DateAminullah Azimi, June 9, 2023
Reviewer Name / DateKenneth Mosman, July 08, 2023