Daily Field Report

Date :07/13/2023
Project No :2023C136
Client Company :Excellere
Arrival Time :07/13/2023 8:00
Onsite Hours :9:30
Name of the Project :Big Creek Boardwalks
Project Location :Alpharetta
Weather :cloudy
Departure Time :07/13/2023 17:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to observe the contractor’s work activities from a quality standpoint to assure compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications.  The following observations were made on site this shift:

Our representative performed observation and documented the drilling and installation of Helical piles this day.  Results are attached in a final report.

Technician Signature / DateAminullah Azimi, July 13, 2023
Reviewer Name / DateKenneth Mosman, July 19, 2023