Density Test Report

Date :11/03/2023
Project No :2021C002
Client Company :CW Matthews
Arrival Time :11/03/2023 8:00
Onsite Hours :03:00
Name of the Project :Runway 9L End Around Taxiway
Project Location :HJAIA
Weather :sunny
Departure Time :11/03/2023 11:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
11/03/2023 1 8.2 120.4 10 119.3 11.5 100.9 98 D6938 Pass
Location : STA 7021+75, Elv/Depth :4 feet below finished grade
Comment : Gauge Serial No. :85759
Technician Signature / DateAminullah Azimi, November 3, 2023
Reviewer Name / DateKenneth Mosman, November 12, 2023