Skip to content

Daily Field Report

Date :12/14/2023
Project No :2023C141
Client Company :Toll Bros
Arrival Time :12/14/2023 12:30
Onsite Hours :02:30
Name of the Project :N. Gate - Old Atlanta Road
Project Location :Cumming
Weather :sunny
Departure Time :12/14/2023 15:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

  • The placement and compaction of backfill soils for road and Lot #32, continued this day.
  • At the time of arrival, our representative observed that work was in progress with one (1) foot lifts being placed and compacted using a 12-ton pad food compactor.
  • Density test results indicate that the compacted materials met the project requirement of 90% of the maximum dry density obtained by the (Standard Proctor ASTM 698),

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateAminullah Azimi, December 14, 2023
Reviewer Name / DateKenneth Mosman, March 09, 2024