Daily Field Report

Date :02/05/2024
Project No :2023C195
Client Company :Toll Bros. Inc.
Arrival Time :02/05/2024 8:30
Onsite Hours :03:00
Name of the Project :Kimbal Bridge Tract
Project Location :Alpharetta
Weather :sunny
Departure Time :02/05/2024 11:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to observe the contractor’s work activities from a quality standpoint to assure compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications.  The following observations were made on site this shift:

  • contractor was recommended under cut the unsuitable locations in the retaining wall #7 footing,
  • performed observation under cut and back fill by suitable metatrail, using trench compaction equipment,

Technician Signature / DateAminullah Azimi, February 5, 2024