Daily Field Report

Date :02/24/2024
Project No :2023C195
Client Company :Toll Bros. Inc.
Arrival Time :02/24/2024 7:30
Onsite Hours :04:30
Name of the Project :Kimbal Bridge Tract
Project Location :Alpharetta
Weather :sunny
Departure Time :02/24/2024 12:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

  • Sunbelt Asphalt. Base course was placed with approximately 6 inches of Cement Treated Base (CTB) from STA 11+00 to STA 15+00.
  • Performed density tests on the top of the outlet of pond #1 and roadway between Lots #9 and #28, between Lots #10 and #29 and between Lots #11 and #30.
  • A sample of the soil cement was taken back to our laboratory for further testing.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateAminullah Azimi, February 24, 2024
Reviewer Name / DateKenneth Mosman, March 15, 2024