Daily Field Report

Date :04/01/2024
Project No :2022C165
Client Company :Toll Bros. Inc.
Arrival Time :04/01/2024 08:30
Onsite Hours :07:15
Name of the Project :Northfield @ Polo Fields - Phase2
Project Location :Pittman Road, Cumming, GA
Weather :Sunny
Departure Time :04/01/2024 15:45
ASEC Technician Name :Fawad Shagiwal

Observations/Finding

As requested the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.

The following observations were observed on the site this day.

    • Construction of Mechanically Stabilized Earth (MSE) Retaining wall was in progressed and 6 steps of the mentioned (MSE) retaining wall was completed and each step has 18 inches height.
    • Work was in progressed with 1 foot lift being placed and compacted at the backfilling area of Mechanically Stabilized Earth (MSE) Retaining wall using sheep food (BW145D) and (BMP8500) equipments.
    • Placement  and compaction of backfill soil at the vicinity of lots# 46 to 49 was in progressed using sheep food (CP56B), (D6K2) and (QT-4) equipments.
    • Excavation operations for temporary pond between lots# 19 and 20 was continued.
    • Density tests results indicated that the compacted materials met the project requirements of 95 percent of the minimum dry density obtained by the (Standard Proctor ASTM 698).

Technician Signature / DateFawad Shagiwal, April 1, 2024