Daily Field Report

Date :04/02/2024
Project No :2022C165
Client Company :Toll Bros. Inc.
Arrival Time :04/02/2024 08:30
Onsite Hours :07:15
Name of the Project :Northfield @ Polo Fields - Phase2
Project Location :Pittman Road, Cumming, GA
Weather :Cloudy
Departure Time :04/02/2024 15:45
ASEC Technician Name :Fawad Shagiwal

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.

The following observations were observed on the site this day.

  • Construction of the Mechanically Stabilized Earth (MSE) retaining wall was in progress with 8 steps of the MSE wall completed, each step having 18 inches in height.
  • Work was in progressed with 1-foot lifts being placed and compacted for the backfilling of the MSE retaining wall using sheep-foot (BW145D) and (BMP8500) equipment.
  • Placement and compaction of backfill soil at the vicinity of MH A7 and MH A8 was in progress using sheeps-foot (CP56B), (D6K2) and (QT-4) equipment.
  • Excavation of soil for the sewer pipe trench between MH A8 to MH C1 progressed.
  • Two layers of 6072 cubic feet rock was placed and compacted in the temporary pond between Lots #19 and 20 using an Excavator (PC390LC), with each layer equal to 3036 cubic feet.
  • One Layer of 1518 cubic feet of soil was placed and compacted at the top of the first layer of rock in the pond between Lots #19 and 20.
  • Density tests results indicated that the compacted materials met the project requirements of 95 percent of the minimum dry density obtained by the (Standard Proctor ASTM 698).

Technician Signature / DateFawad Shagiwal, April 2, 2024
Reviewer Name / DateKenneth Mosman, April 25, 2024