Density Test Report

Date :04/06/2024
Project No :2022C106
Client Company :CWM
Arrival Time :04/06/2024 6:30
Onsite Hours :9:00
Name of the Project :Taxiway 2022 Pavement Replacement
Project Location :HJAIA
Weather :sunny
Departure Time :04/06/2024 15:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
04/06/2024 1 7.2 134.5 GAB 1 135.6 6.8 99.2 95 D6938 Pass
Location : N:9153.472 E: 13993.73 , Elv/Depth :finished grade or Elev: 974.571
Comment : Gauge Serial No. :85759
04/06/2024 2 6.5 134.1 GAB 1 135.6 6.8 98.9 95 D6938 Pass
Location : N: 9152.86 E: 13948.36, Elv/Depth :finished grade or Elev: 975.02
Comment : Gauge Serial No. :85759
04/06/2024 3 5.3 134.2 GAB 1 135.6 6.8 99.0 95 D6938 Pass
Location : N: 9230.05 E: 13952.04, Elv/Depth :Finished grade or 973.906
Comment : Gauge Serial No. :85759
04/06/2024 4 5.9 133.3 GAB 1 135.6 6.8 98.3 95 D6938 Pass
Location : N: 9231.06 E: 14005.89, Elv/Depth :finished grade or 973.34
Comment : Gauge Serial No. :85759
Technician Signature / DateAminullah Azimi, April 6, 2024
Reviewer Name / DateKenneth Mosman, April 25, 2024