Daily Field Report

Date :04/08/2024
Project No :2022C165
Client Company :Toll Bros. Inc.
Arrival Time :04/08/2024 09:45
Onsite Hours :07:00
Name of the Project :Northfield @ Polo Fields - Phase2
Project Location :Pittman Road, Cumming, GA
Weather :Sunny
Departure Time :04/08/2024 16:45
ASEC Technician Name :Fawad Shagiwal

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.

The following observations were observed on the site this day.

  • Construction of the 86-foot long Mechanically Stabilized Earth (MSE) retaining wall was completed.
    First portion: Six steps including one step of foundation, each step with 18 inches of height.
    Second Portion: Five steps, each step with 18 inches of height.
    Third Portion: Five steps, each step with 18 inches of height.
  • Placement and compaction of backfill soil at the vicinity of MH A7 and MH A8 was in progressed using sheeps-foot (CP56B), (D6K2) and (QT-4) equipment.
  • Excavation of soil for the sewer pipe trench between MH A8 to MH A9 was in progress.
  • One layer of 8124.75 cubic feet of rock was placed and compacted in the temporary pond between Lots #19 and #20 using Excavator (PC390LC) equipment.
  • Two layers of 10048 cubic feet dirt or soil was placed and compacted at the top of each layer of rocks in temporary pond between Lots #19 and 20.

Technician Signature / DateFawad Shagiwal, April 8, 2024
Reviewer Name / DateKenneth Mosman, April 26, 2024