Daily Field Report

Date :04/18/2024
Project No :2022C106
Client Company :CWM
Arrival Time :04/18/2024 8:00
Onsite Hours :08:00
Name of the Project :Taxiway 2022 Pavement Replacement
Project Location :HJAIA
Weather :sunny
Departure Time :04/18/2024 16:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative, Amin Azimi visited the job site to observe the contractor’s work activities from a quality standpoint to verify compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications.  The following observations were made on site this shift:

  • Kelly was stripping topsoil East of eastern shoulder and west of western shoulders of the taxiway phase7A to place SQD.
  • BBH installed power line in the above location for lights,
  • Performed straightedge on concrete for lanes 1-4 phase 7A.
  • lab work was performed.
  • performed concrete Coring from lane 1-4,phase7A.
  • lane 1-1, phase 7A, 20.5″, panel 3 from west end.
  • lane 2-1, phase 7A, 21″, panel 2 from west end.
  • lane 3-1, phase 7A, 20.5″, panel 4 from east end.
  • lane 4-1 phase 7A, 22 3/4″, panel 6 from west end.
  • lane 4-2 phase 7A, 22.5″, panel 7 from east end.

In case of any questions or concerns with regards to our observations or recommendations stated in this report we will be more than glad to discuss them with you.

Technician Signature / DateAminullah Azimi, April 18, 2024