Density Test Report

Date :05/01/2024
Project No :2023C180
Client Company :Artisan Communities
Arrival Time :05/01/2024 8:30
Onsite Hours :05:30
Name of the Project :Lakeside Sub. - Lovers Lane, Calhoun
Project Location :Calhoun
Weather :sunny
Departure Time :05/01/2024 14:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
05/01/2024 1 26.1 92.3 P-01 97.0 19.1 95.2 90 D6938 Pass
Location : water storm, 70 feet to east from MHAA4, Elv/Depth :6 feet below finish grade
Comment : Gauge Serial No. :29588
05/01/2024 2 25.8 90.7 P-01 97.0 19.1 93.5 90 D6938 Pass
Location : 21 feet to east from MHAA4, Elv/Depth :6 feet below finish grade
Comment : Gauge Serial No. :29588
05/01/2024 3 27.1 90.4 P-01 97.0 19.1 93.2 90 D6938 Pass
Location : 37 feet to east from MH AA4, Elv/Depth :4 feet below finish grad
Comment : Gauge Serial No. :29588
Technician Signature / DateAminullah Azimi, May 1, 2024