Daily Field Report

Date :09/11/2024
Project No :2023C180
Client Company :Artisan Communities
Arrival Time :09/11/2024 08:00
Onsite Hours :9:30
Name of the Project :Lakeside Sub. - Lovers Lane, Calhoun
Project Location :Calhoun
Weather :
Departure Time :09/11/2024 17:30
ASEC Technician Name :Solomon Cherie

Observations/Finding

Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:

The placement of fill for Lots #125 through #131 continued this day.  Density test results are attached in a separate report.

Please contact us if you have any questions regarding this report or the density test results for today.

 

 

 

Nuclear gauge rading

Backfilled final stage for the day

Technician Signature / DateSolomon Cherie, September 11, 2024
Reviewer Name / DateKenneth Mosman, February 02, 2025