Daily Field Report

Date :09/16/2024
Project No :2023C180
Client Company :Artisan Communities
Arrival Time :09/16/2024 08:30
Onsite Hours :08:45
Name of the Project :Lakeside Sub. - Lovers Lane, Calhoun
Project Location :Calhoun
Weather :
Departure Time :09/16/2024 17:15
ASEC Technician Name :Solomon Cherie

Observations/Finding

Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:

Backfilling of the storm line (b/n BB 9-10) and pipe placement for (BB9-BH1-BH2) and sewer lines (b/n 10.2 & 10.3) continued today.  Density test results are attached in a separate report.

Thirty-two (32) holes were drilled in rock today in preparations for blasting tomorrow (for both the building pad and roadway).

Please contact us if you have any questions regarding this report or the density test results for today.

 

 

 

Storm line BH1-BH2

After blasting

Storm line BB9-BB10

Workers preparing to blast

Technician Signature / DateSolomon Cherie, September 16, 2024
Reviewer Name / DateKenneth Mosman, February 02, 2025