Date :09/24/2024
Project No :2023C180
Client Company :Artisan Communities
Arrival Time :09/24/2024 07:45
Onsite Hours :9:30
Name of the Project :Lakeside Sub. - Lovers Lane, Calhoun
Project Location :Calhoun
Weather :
Departure Time :09/24/2024 17:15
ASEC Technician Name :Solomon Cherie
Observations/Finding
Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:
Backfilling of the storm line manholes AR-3 and BJ-1 and AR-3 and AS-1 and sewer lines between manholes 3.0 and 3.1 continued today. General probing using a 3/8″ diameter probe rod was performed to verify stability of the compacted lift.
Please contact us if you have any questions regarding this report.
Technician Signature / DateSolomon Cherie, September 24, 2024