Skip to content

Daily Field Report

Date :10/07/2024
Project No :2024C116
Client Company :Peeples Owner, LLC
Arrival Time :10/07/2024 09:00
Onsite Hours :08:00
Name of the Project :Peeples Valley Rd, Overlook at Pettit
Project Location :Cartersville
Weather :Sunny
Departure Time :10/07/2024 17:00
ASEC Technician Name :Fawad Shagiwal

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawings/specifications, applicable codes and material submittals.
The following observations were observed on the site this day.

  • Excavation of utility trenches for placement and installation of sewer lines and manholes progressed.
  • Installation and placement of sewer lines and manhole SSA5, SS-P-B1 and SS-P-B2 progressed.
  • The placement and compaction of backfill soils for Lots #74 to #97 progressed with 1-foot lifts being placed and compacted using (CP54B), (RA30), (D61PX) and (CAT330) equipment.

Technician Signature / DateFawad Shagiwal, October 7, 2024
Reviewer Name / DateKenneth Mosman, February 02, 2025