Daily Field Report

Date :10/24/2024
Project No :2024C202
Client Company :CCG
Arrival Time :10/24/2024 07:45
Onsite Hours :9:15
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :
Departure Time :10/24/2024 17:00
ASEC Technician Name :Solomon Cherie

Observations/Finding

Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:

Observed the placement of fill for several lots today. Compaction tests were performed using a nuclear density gauge. Overall, the results of density testing confirmed that fill compaction met the project and ASTM requirements. Results are attached in separate reports.

Please contact us if you have any questions regarding this report or of the density test results.

 

 

 

Picture showing a general lots preparation

The western view showing bldg pad preparation for lots 99&100

Lots 99 and 100 as well as the access road to the other part of the site.

Technician Signature / DateSolomon Cherie, October 24, 2024
Reviewer Name / DateKenneth Mosman, January 09, 2025