Density Test Report

Date :10/28/2024
Project No :2024C168
Client Company :CCG
Arrival Time :10/28/2024 8:30
Onsite Hours :10:00
Name of the Project :Reserve @ Gum Springs
Project Location :Jefferson
Weather :sunny
Departure Time :10/28/2024 18:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
10/28/2024 233 22.1 101.6 26081 102.9 20.0 98.7 95 D6938 Pass
Location : Storm water trench, 48 feet SW from MHC13, Elv/Depth :1 foot below finished grade
Comment : Gauge Serial No. :85759
10/28/2024 234 22.3 98.9 26081 102.9 20.0 96.1 95 D6938 Pass
Location : Storm water trench, 31 feet NE from MHC14, Elv/Depth :2 feet below finished grade
Comment : Gauge Serial No. :85759
10/28/2024 235 22.8 98.8 26081 102.9 20.0 96.0 95 D6938 Pass
Location : Storm water trench, between MHC14 and MHC15, Elv/Depth :2 feet below finished grade
Comment : Gauge Serial No. :85759
10/29/2024 236 20.9 102.2 26081 102.9 20.0 99.3 95 D6938 Pass
Location : Storm water trench, between MHC14 and MHC14.1, Elv/Depth :1.5 feet below finished grade
Comment : Gauge Serial No. :85759
10/28/2024 237 24.1 92.0 26082 94.1 24.3 97.8 95 D6938 Pass
Location : Storm water trench, 48 feet NE from MHC16, Elv/Depth :1 foot below finished grade
Comment : Gauge Serial No. :85759
10/28/2024 238 17.5 98.5 26081 102.9 20.0 95.7 98 D6938 Fail
Location : Roadway between Lot #176 and Lot #187, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/28/2024 239 22.8 92.3 26082 94.1 24.3 98.1 98 D6938 Pass
Location : Roadway between Lot #175 and Lot #180, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/28/2024 240 23.5 92.6 26082 94.1 24.3 98.4 98 D6938 Pass
Location : Roadway between Lot #177 and Lot #178, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/28/2024 241 19.2 122.2 26081 102.9 20.0 99.6 98 D6938 Pass
Location : Roadway between Lot #171 and Lot #181, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/28/2024 242 20.8 101.6 26081 102.9 20.0 98.7 98 D6938 Pass
Location : Roadway between Lot #169 and Lot #182, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/28/2024 243 18 102.8 26081 102.9 20.0 99.9 98 D6938 Pass
Location : Roadway between Lot #184 and Lot #166, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/28/2024 244 20.1 101.4 26081 102.9 20.0 98.5 98 D6938 Pass
Location : Roadway between Lot #192 and Lot #164, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/28/2024 245 22.3 114.3 26082 94.1 24.3 99.4 98 D6938 Pass
Location : 245, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/28/2024 246 22.8 93.9 26082 94.1 24.3 99.8 98 D6938 Pass
Location : Roadway between Lot #192 and Lot #184, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
10/28/2024 247 20.1 101.4 26081 102.9 20.0 98.5 98 D6938 Pass
Location : Roadway between Lot #3 and Lot #188, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
Technician Signature / DateAminullah Azimi, October 28, 2024
Reviewer Name / DateKenneth Mosman, November 05, 2024